Koryx Copper requires an estimated N$34.8 billion (US$2.06 billion) in initial capital investment to develop its Haib Copper Project in Namibia’s //Kharas Region, with construction scheduled to begin in the first quarter of 2028.
The company’s recently completed pre-feasibility study (PFS) estimates that a further N$10.8 billion (US$639 million) will be required in sustaining capital over the mine’s projected 24-year operating life, bringing total capital expenditure to approximately N$45.7 billion.
Koryx Copper President and Chief Executive Officer Heye Daun said the study results had exceeded the company’s initial expectations, with the next 12 months focused on completing a definitive feasibility study (DFS), securing financing and obtaining regulatory approvals.
“The next twelve (12) months will be focused on (i) the completion of the Definitive Feasibility Study (“DFS”), (ii) raising finance, (iii) finishing permitting in preparation for early works commencement late in 2027 and construction commencement in 1Q 2028,” Daun said.
According to the study, the processing plant, including the construction camp and operational facilities, accounts for the largest portion of the initial investment at N$22.3 billion (US$1.32 billion).
Other capital requirements include N$1.8 billion for bulk water supply infrastructure, N$456.8 million for mine housing and N$2.25 billion in project contingency funding.
The study estimates the project’s after-tax net present value at N$42.9 billion, with an internal rate of return of 25% and a projected capital payback period of 3.9 years.
The proposed open-pit mine is expected to produce an average of 135,000 tonnes of copper, 17,000 ounces of gold and 1.22 million pounds of payable molybdenum annually during its first 10 years of operation.
Over its 24-year lifespan, Haib is projected to produce approximately 2.61 million tonnes of copper and generate cumulative after-tax cash flows of N$125.6 billion.
“Total scheduled copper production is approximately 2.61 Mt from sulphide and oxide/transitional material,” the study stated.
The project has an estimated mineral resource containing 4.35 million tonnes of copper, alongside a maiden probable mineral reserve containing approximately three million tonnes of copper.
Koryx plans to undertake a strategic options and project financing review in 2027 while completing the definitive feasibility study to support a final investment decision.
The company expects to secure major regulatory approvals, including a mining licence and environmental clearance certificate, by mid-2027.
Subject to financing and regulatory approvals, preparatory construction activities are expected to begin towards the end of 2027, followed by full construction in the first quarter of 2028.