…targets annual production of 10,000 tonnes of copper equivalent
Consolidated Copper Corp (CCC) is assessing plans to restart production at its Otjihase and Matchless copper mines near Windhoek, targeting annual production of approximately 10,000 tonnes of copper equivalent.
The two mines, collectively known as Central Operations, form part of CCC’s strategy to expand copper production in Namibia through concurrent operations at the mining complex and its Tschudi copper mine.
CCC Chief Executive Officer John Sisay said the company was exploring opportunities to bring Otjihase back into production, although substantial preparatory work was still required.
“We’re looking at how to bring Otjihase back into production, and there’s a great deal of work involved in preparing a mine for its next chapter. We want people to see the site for themselves, meet the team looking after it and understand what we’re working towards,” Sisay said.
The company has not disclosed a definitive timeline for the resumption of production or the overall capital investment required to restart operations.
However, CCC estimates that the existing 1.2-million-tonne-per-annum concentrator at Otjihase could be refurbished in less than six months at a cost of under US$3 million.
The proposed restart plan involves cut-and-fill underground mining at Matchless and room-and-pillar mining at Otjihase.
Central Operations has substantial existing infrastructure, including workshops, a backfill plant, a tailings dam, accommodation facilities and established electricity and water supplies.
Meanwhile, CCC is undertaking a drilling campaign at Matchless to expand its mineral resource base and upgrade existing resource classifications.
The mine currently hosts a mineral resource of 1.7 million tonnes grading 1.97% copper, with the company identifying potential resource growth of approximately 500,000 tonnes.
A further 1.2 million tonnes grading 2% copper could be added at Old Matchless, subject to further exploration, while additional resource growth potential has been identified at Tigerschlucht.
As part of its restart strategy, CCC plans to install a mobile crushing and screening plant and an optical ore-sorting system at Matchless to remove waste material before transporting the pre-concentrated ore 85 kilometres to the Otjihase concentrator.
The company estimates that pre-concentrating ore at Matchless could reduce transport costs by more than 30%.
Located 18 kilometres northeast of Windhoek, Otjihase began producing copper in 1976. CCC acquired the mine alongside the Matchless mining complex following its establishment in 2022.
Central Operations historically produced copper and pyrite concentrates, with silver primarily contained in the copper concentrate.
The proximity of both mines to Windhoek provides access to grid electricity, water supplies and established road and rail infrastructure connecting the operations to port facilities.