Etango bulk earthworks reach 99% as Bannerman targets Q4 FID

by reporter
September 29, 2026
in Uranium
Reading Time: 2 mins read
1.8k 18
A A
988
SHARES
5.8k
VIEWS
Share on Facebook
Share on Twitter
White pickup truck with Bannerman Resources branding in the desert, a man in a hat stands at the edge looking over arid hills under a blue sky.
 

Bannerman Energy says bulk earthworks at its Etango Uranium Project in Namibia are approximately 99% complete, with the final phase expected to be completed before the end of 2026.

The company said early construction works remain on schedule and within budget, with about 523 contractor personnel currently working on site.

Bannerman Managing Director and Chief Executive Officer Gavin Chamberlain said Phase 4 of the bulk earthworks programme began in mid-September and is focused on the process solution ponds and wet plant terraces.

“Construction work on site has continued in line with expectation, with our four Namibian contractors performing consistently well and aligned to both schedule and cost. The final phase of the large-scale bulk earthworks package is expected to be complete before year end, representing a key milestone in our early works activities and the overall development of Etango,” Chamberlain said.

The project recorded 1.6 million working hours without a lost-time injury before its first lost-time injury was recorded in September.

Meanwhile, production of heap-leach drainage aggregate has reached about 50% of the total requirement, with the material being stockpiled ahead of placement.

Concrete works are also progressing across the primary crusher and dry plant infrastructure. About 14,700 cubic metres of concrete has been cast under the Phase 1 and Phase 2A packages, representing 86% of the planned volume.

Bannerman said dry plant design is approximately 98% complete, while detailed structural engineering for the wet plant has reached 33%.

Phase 1 of the permanent water supply pipeline is about 90% complete, while design work for the Walvis Bay acid storage and handling facility has reached 53%.

The construction progress comes as Bannerman prepares to make a Final Investment Decision (FID) on Etango in the fourth quarter of 2026, following completion of its strategic investment and joint venture transaction with CNNC Overseas Limited (CNOL).

“The early works programme, and particularly the bulk earthworks contract, has been a seminal workstream in maintaining the critical path timeline for Etango,” Chamberlain said.

“With the completion of the CNOL strategic investment and joint venture transaction last week, we are making final preparations towards a targeted Final Investment Decision on Etango during Q4 2026.”

He said the FID is expected to be followed promptly by the start of full-scale construction.

The Etango Uranium Project is located in Namibia’s Erongo Region and is being developed through a joint venture between Bannerman and CNOL.

Related Posts

Map of the NOVA JV project area along the Namibian coast showing three labeled sites—Namaqua, Iguana, and Barking Gecko—with arrows pointing to each site and a shaded polygon marking the NOVA JV PROJECT AREA near Walvis Bay.

Core Energy Minerals begins drilling at Namibia’s Barking Gecko uranium prospect

November 12, 2026
5.8k
Tile showing Uranium (U, atomic number 92) beside a yellow uranium ore on a black reflective surface.

Namibia earns N$3.4 billion from uranium exports to China in September

November 10, 2026
5.8k
Industrial drilling rig captured from ground level, showing metal rails, gears and hydraulic components reaching toward the sky.

Arkle begins second-phase drilling at Namibia’s Onyofi uranium project

November 10, 2026
5.8k
Group of professionals in business attire gather outside a modern white building with the IAEA logo on the wall and a red carpet under a bright blue sky.

IAEA raises groundwater protection concerns over Namibia uranium pilot project

November 9, 2026
5.8k
Langer Heinrich Mine records 33% rise in uranium production

Langer Heinrich uranium mine generates N$1.52bn in quarterly revenue

November 6, 2026
5.8k
Map showing Skeleton Coast uranium projects with mines (Rössing, Husab, Bannerman, Langer Heinrich) and EPL blocks EPL8617, EPL9873, EPL9727, EPL8208, EPL9872; Swakopmund and Walvis Bay Port labeled.

Skeleton Coast Uranium raises N$40.8m to advance exploration in Namibia

November 6, 2026
5.8k

Recommended

Close-up portrait of a man with glasses and a beard, wearing a dark suit against a dark background.

Namibia’s oil test:Why rejecting stabilisation clauses is the right fight

1 month ago
6.2k
Diamond sector applauded for youth development

Diamond sector applauded for youth development

3 years ago
5.8k
Load More

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
  • Login
No Result
View All Result
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPERREADER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.