Etango bulk earthworks reach 66.5% as project stays on schedule

by reporter
April 9, 2026
in Uranium
Reading Time: 2 mins read
1.8k 19
A A
 

Bannerman Energy says bulk earthworks at its Etango Uranium Project have reached 66.5% completion, with the development remaining on track in terms of both budget and schedule.

According to the company’s March update, construction activity is currently focused on the heap leach pad and associated ponds, while work has also progressed across the wet plant terraces.

A key component of the processing infrastructure, the blasting, crushing and screening of heap leach drainage aggregate, is advancing as planned, with 24% of the required material already stockpiled.

“The bulk earthworks continue to progress in line with schedule and are now approximately 66.5% complete. Work remains focused on the heap leach pad and ponds, with activities now also advancing across the wet plant terraces. The blasting, crushing and screening of heap leach drainage aggregate is advancing to schedule, with drainage material being stockpiled for later placement on the heap leach pad,” the company said.

Concrete works are also progressing steadily, with more than 5,500 cubic metres poured across the site to date. Phase one of the primary crusher structure is well advanced, with foundations and first-level walls completed.

Phase 2A, covering dry plant infrastructure such as the stockpile tunnel and fine ore silo, has reached 32% completion, with wall construction underway.

The installation of the permanent water supply pipeline is ahead of schedule, with the first phase 70% complete.

Foundations for the Swakop River pipe bridge and the main pump station have been completed, marking progress in securing the site’s water infrastructure.

Earthworks and excavations for the booster pump station terraces and pipeline have also commenced and are progressing in line with schedule.

On the technical side, Bannerman Energy has completed model reviews for the dry plant, with outcomes being implemented to support upcoming construction tenders and strengthen the project’s engineering framework.

“These areas include the stockpile tunnel, secondary and tertiary crushing and screening facilities, and the fine ore silo. The stockpile tunnel foundation is complete, with wall construction now underway. Wall bases for the crushing and screening facilities and silo have also been finalised,” the company said.

The project currently employs more than 560 contractor personnel from four local Namibian firms. The company said safety remains a priority, supported by ongoing campaigns and monthly recognition programmes across the workforce.

MUST READ

Tumas Uranium project nears full construction readiness

Deep Yellow delays Tumas uranium project over weak market conditions

November 22, 2026
5.8k
Row of large blue barrels labeled 'Low Specific Activity (LSA-1) UN 2912' in an industrial storage area, with safety barriers nearby.

Langer Heinrich generates N$5.16bn in uranium sales

November 17, 2026
5.8k
Map of the NOVA JV project area along the Namibian coast showing three labeled sites—Namaqua, Iguana, and Barking Gecko—with arrows pointing to each site and a shaded polygon marking the NOVA JV PROJECT AREA near Walvis Bay.

Core Energy Minerals begins drilling at Namibia’s Barking Gecko uranium prospect

November 12, 2026
5.8k
Tile showing Uranium (U, atomic number 92) beside a yellow uranium ore on a black reflective surface.

Namibia earns N$3.4 billion from uranium exports to China in September

November 10, 2026
5.8k
Industrial drilling rig captured from ground level, showing metal rails, gears and hydraulic components reaching toward the sky.

Arkle begins second-phase drilling at Namibia’s Onyofi uranium project

November 10, 2026
5.8k
Group of professionals in business attire gather outside a modern white building with the IAEA logo on the wall and a red carpet under a bright blue sky.

IAEA raises groundwater protection concerns over Namibia uranium pilot project

November 9, 2026
5.8k
Next Post
Elevate Uranium ships pilot plant to Namibia, expands drilling at Koppies

Elevate Uranium sets August 2026 target for pilot plant results

Namibia’s mining exports slump by N$4.4bn in February amid broad commodity decline

Namibia’s mining exports slump by N$4.4bn in February amid broad commodity decline

Recommended

SAIMM to relaunch in Namibia, Aipanda elected interim chair

SAIMM to relaunch in Namibia, Aipanda elected interim chair

Navigating uncertainty: Gold’s enduring appeal in a fractured world

Navigating uncertainty: Gold’s enduring appeal in a fractured world

AfriTin shareholders approve name change to Andrada Mining

AfriTin shareholders approve name change to Andrada Mining

Woman in colorful traditional attire speaking into a handheld microphone at a panel discussion.

Namibia pitches critical minerals, green energy to Chinese investors

Mining leads Namibia’s exports with N$4.3 billion surge in September

Mining leads Namibia’s exports with N$4.3 billion surge in September

Namibia’s diamond production declines by 11% in Q2 

Namibia’s diamond production declines by 11% in Q2 

Load More

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
  • Login
No Result
View All Result
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPERREADER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.