• Mining
Saturday, September 12, 2026
Mining and Energy Namibia | Namibia’s Leading Mining & Energy News
Subscribe
No Result
View All Result
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPERREADER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPERREADER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc
No Result
View All Result
Mining and Energy Namibia | Namibia’s Leading Mining & Energy News
No Result
View All Result
Home Uranium

Etango bulk earthworks reach 66.5% as project stays on schedule

by reporter
April 9, 2026
in Uranium
1.8k 19
A A
0
 

Bannerman Energy says bulk earthworks at its Etango Uranium Project have reached 66.5% completion, with the development remaining on track in terms of both budget and schedule.

According to the company’s March update, construction activity is currently focused on the heap leach pad and associated ponds, while work has also progressed across the wet plant terraces.

A key component of the processing infrastructure, the blasting, crushing and screening of heap leach drainage aggregate, is advancing as planned, with 24% of the required material already stockpiled.

“The bulk earthworks continue to progress in line with schedule and are now approximately 66.5% complete. Work remains focused on the heap leach pad and ponds, with activities now also advancing across the wet plant terraces. The blasting, crushing and screening of heap leach drainage aggregate is advancing to schedule, with drainage material being stockpiled for later placement on the heap leach pad,” the company said.

Concrete works are also progressing steadily, with more than 5,500 cubic metres poured across the site to date. Phase one of the primary crusher structure is well advanced, with foundations and first-level walls completed.

Phase 2A, covering dry plant infrastructure such as the stockpile tunnel and fine ore silo, has reached 32% completion, with wall construction underway.

The installation of the permanent water supply pipeline is ahead of schedule, with the first phase 70% complete.

Foundations for the Swakop River pipe bridge and the main pump station have been completed, marking progress in securing the site’s water infrastructure.

Earthworks and excavations for the booster pump station terraces and pipeline have also commenced and are progressing in line with schedule.

On the technical side, Bannerman Energy has completed model reviews for the dry plant, with outcomes being implemented to support upcoming construction tenders and strengthen the project’s engineering framework.

“These areas include the stockpile tunnel, secondary and tertiary crushing and screening facilities, and the fine ore silo. The stockpile tunnel foundation is complete, with wall construction now underway. Wall bases for the crushing and screening facilities and silo have also been finalised,” the company said.

The project currently employs more than 560 contractor personnel from four local Namibian firms. The company said safety remains a priority, supported by ongoing campaigns and monthly recognition programmes across the workforce.

author avatar
reporter
See Full Bio
Share396Tweet247

Related Posts

Bannerman switches Etango uranium project to live power
Uranium

Bannerman raises N$1.43bn to fully fund Etango Uranium Project

  Bannerman Energy has completed a fully underwritten N$1.43 billion (A$124 million) share placement to fund the development, construction and...

September 10, 2026
Welcome arch at a uranium mine entrance with signage for Rössing Uranium Limited and ENNC logo in blue.
Uranium

IDC’s 10.2% Rössing Uranium stake draws 35 potential investors

  The Industrial Development Corporation’s (IDC) proposed disposal of its 10.2% stake in Rössing Uranium has attracted 35 expressions of...

September 7, 2026

Recommended

Pancontinental raises oil resource estimate at PEL 87 to 2.5 billion barrels

GEO advances talks to farm out Namibia offshore licence

8 months ago
Africa urged to balance green hydrogen exports and local industry development

Africa urged to balance green hydrogen exports and local industry development

3 years ago
Load More
Black transparent logo for dark mode

About Us

The Namibia Mining and Energy website is a comprehensive online platform dedicated to showcasing Namibia's mining and energy sectors

Categories

  • Copper
  • Diamonds
  • Energy
  • Gold
  • Green Hydrogen
  • Lithium
  • Mining
  • Namibia
  • News
  • Oil & Gas
  • Opinions
  • Tin
  • Uranium
  • Zinc

Get in touch

Email:newsdesk@miningandenergy.com.na

© 2026 Mining and Energy | All Rights Reserved. The Namibia Mining and Energy website is a comprehensive online platform dedicated to showcasing Namibia's mining and energy sectors.

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc

© 2026 Mining and Energy | All Rights Reserved. The Namibia Mining and Energy website is a comprehensive online platform dedicated to showcasing Namibia's mining and energy sectors.