Paladin Energy completes Langer Heinrich Mine restart project within N$2.2b budget 

by editor
July 22, 2024
in Uranium
Reading Time: 2 mins read
1.8k 77
A A

Paladin Energy has completed the restart project at its Langer Heinrich Mine (LHM) in Namibia on time and within budget, with a total expenditure of N$2,2 billion (US$119.7 million). 

The uranium exploration and development company’s Chief Executive Officer, Ian Purdy, said the project was completed with no serious safety or environmental incidents reported.

“We are exceptionally pleased to report the completion of the Langer Heinrich Mine Restart Project. The project’s successful execution, both on time and within budget, reflects the dedication and hard work of our entire team. This achievement positions us well for a successful ramp-up of production at the mine.” he said.

A release by Paladin Energy revealed that the full-scale mining operations at Langer Heinrich are expected to resume in FY2026, with the goal of achieving nameplate production of 6 million pounds of U3O8 per annum by the end of calendar year 2026.

“The LHM will be in operational ramp up during FY2025, with ore feed sourced from previously mined stockpiled ore. Production levels are expected to be higher in the second half of the year. Mining activities are expected to re-commence in FY2026 ahead of achieving nameplate production of 6Mlb p.a by the end of CY2026,” said Purdy.

He further explained that while initial production utilises stockpiled ore, the LHM is currently ramping up and is expected to reach 4.0-4.5 million pounds of uranium oxide (U3O8) in 2025.

The first shipment of uranium concentrate, containing 319,229lb of U3O8, departed Namibia in July 2024.

“It is exceptionally pleasing to deliver our first quarterly production update since returning the Langer Heinrich Mine to production, the Langer Heinrich operations team has done an exceptional job in delivering early production and the operational knowledge gained has underpinned our FY2025 production guidance between 4.0 to 4.5Mlb of U3O8,” he said.

Furthermore, Paladin currently has N$896.1 million (US$48.9 million) in cash and cash equivalents, along with access to an untapped N$1.4 billion (US$80 million) credit facility.

The company also received a N$454.5 million (US$24.8 million) partial advance payment from a customer.

Danielle Lazarov was appointed as the company’s Chief People & Corporate Affairs Officer and in April 2024, Paladin consolidated its shares on a 10-for-one basis.

Paladin is an ASX 200 listed uranium company with its head office in Perth, Western Australia. It holds a 75% interest in the Langer Heinrich Mine in Namibia.

MUST READ

Tumas Uranium project nears full construction readiness

Deep Yellow delays Tumas uranium project over weak market conditions

November 22, 2026
5.8k
Row of large blue barrels labeled 'Low Specific Activity (LSA-1) UN 2912' in an industrial storage area, with safety barriers nearby.

Langer Heinrich generates N$5.16bn in uranium sales

November 17, 2026
5.8k
Map of the NOVA JV project area along the Namibian coast showing three labeled sites—Namaqua, Iguana, and Barking Gecko—with arrows pointing to each site and a shaded polygon marking the NOVA JV PROJECT AREA near Walvis Bay.

Core Energy Minerals begins drilling at Namibia’s Barking Gecko uranium prospect

November 12, 2026
5.8k
Tile showing Uranium (U, atomic number 92) beside a yellow uranium ore on a black reflective surface.

Namibia earns N$3.4 billion from uranium exports to China in September

November 10, 2026
5.8k
Industrial drilling rig captured from ground level, showing metal rails, gears and hydraulic components reaching toward the sky.

Arkle begins second-phase drilling at Namibia’s Onyofi uranium project

November 10, 2026
5.8k
Group of professionals in business attire gather outside a modern white building with the IAEA logo on the wall and a red carpet under a bright blue sky.

IAEA raises groundwater protection concerns over Namibia uranium pilot project

November 9, 2026
5.8k
Next Post
Galp invests N$2.1bn in Namibian upstream projects in six months

Galp invests N$2.1bn in Namibian upstream projects in six months

Trigon Metals secures working capital advance for Kombat Mine 

Trigon Metals secures working capital advance for Kombat Mine 

Recommended

Galp Energia invests N$1.5bn in Namibian upstream projects in Q1

Galp Energia invests N$1.5bn in Namibian upstream projects in Q1

Kaoko Metals launches N$107m IPO to advance copper exploration in Namibia

Kaoko Metals launches N$107m IPO to advance copper exploration in Namibia

Namibia to conduct Namibia-South Africa green hydrogen pipeline feasibility study

Namibia to conduct Namibia-South Africa green hydrogen pipeline feasibility study

Offshore oil rig/platform floating on calm blue ocean under a clear sky, with a tall drilling tower.

Shell contract ends as Deepsea Mira heads to Walvis Bay for upgrades

Zimplats invests R28 billion into new mine and solar power plant

Zimplats invests R28 billion into new mine and solar power plant

Treasury kicks off mid-term budget review consultations

Treasury kicks off mid-term budget review consultations

Load More

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
  • Login
No Result
View All Result
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPERREADER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.