• Mining
Wednesday, March 11, 2026
Mining and Energy Namibia | Namibia’s Leading Mining & Energy News
Subscribe
No Result
View All Result
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPERREADER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPERREADER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc
No Result
View All Result
Mining and Energy Namibia | Namibia’s Leading Mining & Energy News
No Result
View All Result
Home Uranium

Deep Yellow spends N$160 million in Q1 to progress Tumas project

by editor
April 22, 2025
in Uranium
1.8k 56
A A
0

Deep Yellow has revealed that it spent N$160 million on development activities at its flagship Tumas project in Namibia during the first quarter of the year.

The company’s latest optimisation work at the Tumas project has resulted in a uranium price of US$82.50 per pound (lb) of U3O8. According to Deep Yellow, this price further supports Tumas’ economic viability and reinforces its standing as a Tier-1, long-life uranium operation. The Net Present Value (NPV) post-tax is currently estimated at N$1.08 billion (US$577 million), while the internal rate of return (IRR) post-tax stands at 19%.

Initial Capital Expenditure (CAPEX) for the project is estimated at N$893 million (US$474 million), while the C1 operational expenditure (OPEX) for the first 20 years is reported at US$24.52 per tonne of ore treated, or US$35.02 per lb of U₃O₈.

Despite the significant expenditure, no mining production activities took place during the quarter. This was due to a delayed Final Investment Decision (FID), prompted by insufficient uranium price incentives to justify the development of a greenfield project. The Deep Yellow Board has, however, approved a staged development approach, with detailed engineering and early works continuing.

“The Tumas Project is ready to take the next step towards development, but as we have consistently stated, a healthy prevailing uranium market is a key prerequisite. The final project approval will therefore be delayed until uranium prices fully reflect a sustainable incentivisation environment essential to encourage the development of new projects for much-needed additional production,” said John Borshoff, Managing Director of Deep Yellow.

Borshoff said the company would focus on other aspects of the Tumas project, such as early works infrastructure and detailed engineering, but would not commit capital to the construction of the process plant until uranium prices improve.

By the end of the first quarter of 2025 (31 March), a pre-mining, grade control drilling programme, which began in August 2024 with three Reverse Circulation (RC) rigs operating at Tumas 3, had completed 2,802 holes for a total of 39,348 metres. This drilling covered the small open pits south of and near the proposed plant site.

“This work will prepare tailings deposition sites for utilisation and be in readiness for plant commissioning and the ramp-up phase of the operation. This drill programme is planned to continue until the end of April 2025,” the company said.

At present, two RC rigs are in operation, and the overall drilling programme is expected to require approximately 41,000 metres of drilling.

The construction schedule for the process plant has been extended from 18 to 24 months, with the production ramp-up period also increasing from six months to 15 months. The company estimates that wet commissioning will be completed within 24 months of the FID decision, with ore processing and production ramp-up following shortly thereafter.

“First product into drums is anticipated approximately two months after ore processing commences. The schedule estimated for Tumas is considered conservative and will be further refined during the ongoing detailed engineering,” Deep Yellow said.

 

 

author avatar
editor
See Full Bio
Share395Tweet247

Related Posts

Mining Index rebounds in July on zinc and diamond output
Uranium

Mining leads Namibia’s environmental applications as uranium projects dominate

  Mining projects account for the largest share of environmental applications currently under review in Namibia, with uranium developments leading...

March 1, 2026
IAEA findings to guide Namibia’s decision on Omaheke uranium project clearance
Uranium

IAEA findings to guide Namibia’s decision on Omaheke uranium project clearance

  Namibia’s Environmental Commissioner, Timoteus Mufeti, says findings from an International Atomic Energy Agency (IAEA) study into the proposed in-situ...

February 25, 2026

Recommended

Namibia’s Competition Commission clears N$418m sale of Kombat Mine to Horizon

Namibia’s Competition Commission clears N$418m sale of Kombat Mine to Horizon

6 months ago
Stamper finalises BISP transaction, Lüderitz Basin drilling set for November

Stamper Oil & Gas eyes strategic gains as supermajors move into Lüderitz Basin

4 weeks ago
Load More

Newsletter

Black transparent logo for dark mode

About Us

The Namibia Mining and Energy website is a comprehensive online platform dedicated to showcasing Namibia's mining and energy sectors

Categories

  • Copper
  • Diamonds
  • Energy
  • Gold
  • Green Hydrogen
  • Lithium
  • Mining
  • Namibia
  • News
  • Oil & Gas
  • Opinions
  • Tin
  • Uranium
  • Zinc

Get in touch

Email:newsdesk@miningandenergy.com.na

© 2026 Mining and Energy | All Rights Reserved. The Namibia Mining and Energy website is a comprehensive online platform dedicated to showcasing Namibia's mining and energy sectors.

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Diamonds
  • Oil & Gas
  • Uranium
  • Green Hydrogen
  • E-PAPER
  • Gold
  • Lithium
  • Energy
  • Copper
  • Zinc

© 2026 Mining and Energy | All Rights Reserved. The Namibia Mining and Energy website is a comprehensive online platform dedicated to showcasing Namibia's mining and energy sectors.